The Challenge For Softech
On the High Speed-1 Channel Tunnel line, the Purfleet Station Level Crossing Replacement project was initiated to enhance safety and improve transportation efficiency by replacing an existing level crossing with a highway bridge. This required the lowering of Overhead Line Electrification (OLE) catenaries to ensure proper clearance between the new highway bridge and the electrification system.
Softech’s Solution
Softech overcame the OLE clearance challenge at the new highway overbridge by conducting a detailed feasibility study to assess the technical and safety implications of lowering the catenary. The proposed solution was documented and submitted for GRIP 3 approval, incorporating feedback to finalise the design



Feedback
Manoj Gupta
“Really pleased with Softech’s Teams’ proactive approach and always going the extra mile to keep the quality, cost and program on target.”